Uganda: Parliament Faults Ageing Network for Persistent Power Outages
Persistent electricity outages have been linked to an ageing and increasingly overloaded distribution network, with a parliamentary inquiry finding that nearly half of the country's power transformers have exceeded 30 years of service.
In its report on persistent power supply interruptions, Parliament's Committee on Environment and Natural Resources found that 47 per cent of Uganda Electricity Distribution Company Limited's (UEDCL) power transformers are more than 30 years old, while 74 per cent of distribution transformers have poor or no protection.
The findings point to mounting pressure on infrastructure struggling to keep pace with growing electricity demand, raising the risk of equipment failures and prolonged interruptions for households and businesses.
The committee also found that 12 substations are operating above 80 per cent of their loading capacity, with Mutundwe operating at 130.2 per cent, Busunju at 124.2 per cent and Kajjansi at 104.6 per cent.
Follow us on WhatsApp | LinkedIn for the latest headlines
It warned that the condition of the equipment makes the network increasingly vulnerable to faults, particularly where protection systems are inadequate.
"The Committee observes that 74% of distribution transformers have poor or no protection, which explains in part the high transformer failure rate of 6 per cent against a target of 4 per cent," the report states.
Faulty protection relays and battery systems further increase the risk of local faults spreading into wider electricity interruptions, according to the committee.
The strain is being compounded by rising demand. Domestic maximum demand increased from 986.38MW in April 2025 to 1,187.68MW in February 2026, representing growth of about 20 per cent in less than a year.
However, expansion and rehabilitation of the distribution network have not kept pace.
The committee identified 13 medium-voltage feeders operating above their design capacity, including the Kampala South-Kigo 11kV feeder at 143.3 per cent and the Namungoona-Nansana 11kV feeder at 126.9 per cent.
Distribution losses also stood at 17.9 per cent, above the regulatory target of 13.65 per cent.
Overgrown vegetation was identified as the most common single cause of faults, alongside ageing equipment, overloaded transformers, defective protection systems and inadequate maintenance.
The findings echo concerns raised in earlier reports about UEDCL's operational difficulties following its takeover of electricity distribution from Umeme in April 2025.
UEDCL assumed full control of electricity distribution on April 1, 2025, following the expiry of Umeme Limited's 20-year concession, which the government had decided in 2022 not to renew as part of efforts to return distribution infrastructure to state management and reduce electricity costs.
However, the transition came at a difficult time for the sector, with the network requiring substantial rehabilitation and new investment.
An internal UEDCL status report subsequently revealed that capital investments in the distribution network had been restricted for about three years following the government's decision not to renew Umeme's concession, leaving infrastructure in what the utility described as dire need of investment.
This meant UEDCL inherited not just a nationwide distribution network and millions of customers, but also years of accumulated infrastructure weaknesses that would test its technical, financial and operational capacity.
The report also documented thousands of hours of outages between May 2025 and March 2026, resulting in the loss of 20.75 gigawatt-hours of electricity valued at approximately Shs12.33 billion.
The Electricity Regulatory Authority (ERA) has acknowledged that restoring reliable supply will require time and substantial investment.
In October, ERA director of corporate and consumer affairs Julius Wandera said improvements would not happen immediately.
"The resolution of power outages is gradual. It is not something that can be done in one day," Wandera said.
The regulator projected that outages could begin easing within three months, with more significant improvements expected within six months. Major infrastructure interventions, however, could take between 18 months and two years.
UEDCL has attributed the challenges partly to rapid customer growth, years of inadequate investment in the distribution network and procurement delays. The utility says it is replacing faulty transformers, upgrading overloaded substations, reconfiguring distribution lines and recruiting additional technicians.
The government allocated about US$129 million to UEDCL across the 2025 and 2026 financial years, while the utility has a five-year investment plan worth approximately US$994.5 million through 2030.

Sign up for free AllAfrica Newsletters
Get the latest in African news delivered straight to your inbox
The transition from Umeme has also attracted political scrutiny. In August, Public Accounts Committee chairperson Patrick Nsamba questioned why electricity service delivery had deteriorated despite UEDCL inheriting the distribution network and much of the former operator's workforce.
"When you inherited Umeme's business, things have become worse. Ugandans are experiencing a worse situation than in the days of Umeme," Nsamba said during a meeting with energy sector officials, according to Uganda Radio Network.
UEDCL has maintained that it inherited a network already weakened by years of insufficient investment and growing demand.
Beyond reliability, the parliamentary inquiry highlighted delays in extending electricity access. It found that 232,586 applicants who had fully paid for connections were still awaiting connection as of July 31, 2026.
The committee recommended that the Ministry of Energy, UEDCL and the Uganda Electricity Transmission Company Limited provide regular updates on approved asset replacement and substation upgrade projects, including expenditure, implementation progress and measurable improvements in power supply.