How data centre growth impacts Ireland's climate targets
Data centres in Ireland were responsible for more than 1.7 million tonnes of carbon dioxide emissions in 2025, an analysis by RTÉ Investigates has found.
That's equivalent to just under 40% the average annual cut in greenhouse gas emissions Ireland needs to make between 2025 and 2030 to meet its climate targets.
Electricity use accounted for about 1.71 million tonnes of carbon dioxide emissions last year, but two new data centre sites, powered largely by gas, have since become operational. EPA filings indicate they will add at least 400,000 tonnes of carbon dioxide emissions a year to the figure.
RTÉ Investigates also examined plans for eight more data centre developments, four of which are already under construction.
If all eight go ahead, they could more than double the sector’s annual emissions to between 4.5 million and 6 million tonnes once fully operational.
The findings are part of a wider RTÉ Investigates examination of Ireland’s data centres. RTÉ Investigates: The People v Data Centres airs at 9.35pm on Monday 30 November on RTÉ One and RTÉ Player.
Biggest users
Amazon was the biggest user of grid electricity in the analysis. Its data centres drew more electricity than all the other facilities in the analysis combined, accounting for just over half of the estimated emissions from electricity use.
In a statement to RTÉ Investigates, Amazon said: "Data centre electricity use in Ireland reflects the efficiency of the facilities, the energy sources powering them, and the value they return to the grid and local communities - not just the total amount drawn."
RTÉ Investigates analysed electricity use reported to the Environmental Protection Agency (EPA) by operators of Ireland’s largest data centres.
Those facilities used 7.88 terawatt hours (TWh) in 2025, while smaller data centres used an estimated 0.78 TWh, based on company disclosures and planning documents.
The analysis used separate emissions factors from the Sustainable Energy Authority of Ireland (SEAI) to estimate emissions from grid electricity.
We need your consent to load this flourish contentWe use flourish to manage extra content that can set cookies on your device and collect data about your activity. Please review their details and accept them to load the content.Manage Preferences
Twenty-three operational hyperscale campuses, designed to provide computing power and data storage on a very large scale, hold industrial emissions licences from the EPA or have applied for them. Most of these campuses contain several data centres.
Of the estimated 1.71 million tonnes of carbon dioxide emissions associated with grid electricity use across the analysis, about 1.55 million tonnes came from electricity used by hyperscale campuses.
But there are several smaller facilities that are not required to register for industrial emissions licences.
RTÉ Investigates identified at least 22 such facilities.
Based on company disclosures and planning documents, those facilities drew an estimated 777 gigawatt hours (GWh) of electricity from the grid, associated with about 153,000 tonnes of carbon dioxide emissions.
Two additional data centre campuses that opened this year, operated by Echelon and EdgeConnex, are largely powered by gas, and look set to add at least 400,000 tonnes of emissions, according to EPA filings.
To meet its 2030 climate targets, Ireland would need to cut its annual greenhouse gas emissions by an average of about 4.4 million tonnes of carbon dioxide equivalent each year between 2025 and 2030.
In a statement to RTÉ Investigates, the Department of Climate, Energy and the Environment said Government policy supports both decarbonisation and digitalisation, and that it supports data centre development "in a sustainable and managed way".
"On the back of our climate action implementation, Ireland now has the lowest level of greenhouse gas emissions in 36 years, despite significant population and economic growth in that time," the department said.
Four of the planned developments are under construction. Two have planning permission, but construction has yet to begin, and two are under appeal with An Coimisiún Pleanála.
Separately, Waterford County Council refused planning permission for another proposed data centre in October. The developer, Echelon, has appealed the decision.
Electricity use is already rising at existing sites. EPA filings show that operational hyperscale data centres used 14% more electricity in 2025 than in 2024.
"The emissions impact of data centres are offsetting any gains we are making in other sectors," Hannah Daly, a Professor of Sustainable Energy at University College Cork, said.
"The emissions of data centres in 2025 calculated here is more than four times greater than the emissions saved from all fully electric vehicles that were on the road last year. This trend is likely to get worse, as data centres are being built with on-site fossil fuel power plants to meet their energy needs," Prof Daly added.
Based on figures provided to RTÉ Investigates by Eirgrid, if Ireland’s existing data centres ran at 100% capacity year-round, they would use more than half of Ireland’s current electricity output.
'Glide path'
The Government published its Large Energy User Action Plan in January, following a decision by the Commission for Regulation of Utilities (CRU) on how new data centres can connect to the grid.
Under the CRU’s rules, new data centres covered by the policy must meet at least 80% of their annual electricity demand with additional renewable electricity generated in the Republic.
But they have six years from the date their grid connection is switched on to meet that requirement. During this transition period, known as a "glide path", they can still burn fossil fuels to generate electricity.
In a statement to RTÉ Investigates, the CRU said delays to renewable energy projects can arise from circumstances beyond data centre operators’ control.
It said EirGrid and ESB Networks will develop a framework for assessing whether data centres have met the renewables requirement and what action is appropriate if they fall short. That could include limiting or cancelling a data centre’s grid connection.
The Large Energy User Action Plan is being challenged in the High Court by environmental groups who argue that it will "lock Ireland into decades of greenhouse gas emissions."
"The six-year glide path is very ambitious," Dr Aideen O’Dochartaigh, an expert in sustainability accounting and responsible business at Dublin City University (DCU), told RTÉ Investigates.
"It’s great we now have a policy, but it gives Eirgrid and ESB Networks plenty of flexibility to delay and push out the six-year target."
Prof Daly said the six-year transition period means that new data centres could be operating largely on fossil fuel generation "well into the 2030s."
In a statement to RTÉ Investigates, the Department of Climate, Energy and the Environment said the Government’s Large Energy User Action Plan sets out a "plan-led" approach to major energy-intensive investments, including data centres.
The department said this approach would ensure that growth is "aligned with Ireland’s green transition".
Responding to concerns that new data centres could prolong Ireland’s reliance on fossil fuels, Una Fitzpatrick of Cloud Infrastructure Ireland, which represents Ireland’s largest data centre operators, told RTÉ Investigates that data centres are "part of the solution" because they help attract investment in renewable electricity.
"Renewables aren't cheap to build and develop, so the investors need to know that there are customers there ready to take that energy that they create, and that's the kind of guarantee or the anchor that the data centres provide," Ms Fitzpatrick said.
Other industry advocates say that Ireland’s climate targets are unrealistic.
Mark Foley, the former Eirgrid chief executive who has lobbied on behalf of the data centre industry since leaving his role, said in a submission to the CRU in 2025 that "climate targets were never realistic in the first place" and that Ireland risked "sacrificing a major section of our economy" - data centres – by attempting to meet them.
In a joint report in March 2025, the Irish Fiscal Advisory Council and the Climate Change Advisory Council estimated that Ireland could have to pay €8bn to €26bn to other EU countries if it fails to step up action to meet its EU climate commitments.
The direct economic contribution of data centres to Ireland is difficult to quantify. Jobs figures cited by the Government range from 50,000 to 875,000 jobs created indirectly or "underpinned" by the industry.
The industry as a whole, however, is a critical part of the modern global economy, powering everything from streaming services to financial transactions, and enabling remote working through applications like cloud storage and video conferencing.
"Those companies who run and operate data centres are much bigger employers and in the broader sense they employ a lot of engineers, a lot of R&D, a lot of innovation happens in those companies here in Ireland, and we should be very proud of that," Ms Fitzpatrick said.
"They're bringing new renewable projects... they are making tangible, very significant investments into the Irish economy, and I think for generations to come, if we can get this right now, there will be huge benefits."
Watch RTÉ Investigates: The People v Data Centres from Joe Galvin and producer/director Philip Gallagher on 30 November on RTÉ One and RTÉ Player.