GRIDCo restores power to parts of Ashanti and Western regions after chainsaw operators damage transmission line
The Ghana Grid Company (GRIDCo) has successfully restored the damaged 330kV Aboadze–Anwomaso transmission line, which tripped and caused power o…
The Ghana Grid Company (GRIDCo) has successfully restored the damaged 330kV Aboadze–Anwomaso transmission line, which tripped and caused power outages in parts of the Ashanti and Western Regions after illegal chainsaw operators felled a tree onto it.
According to a press statement issued by GRIDCo, the incident occurred on Wednesday, November 25, 2026, when a large tree was felled onto a section of the transmission line between Tower 268 and Tower 269.
The damage forced system operators to reduce power supply to parts of Kumasi due to the unavailability of the critical line.
Following the trip, GRIDCo engineers undertook investigations and carefully patrolled the affected section to ascertain the cause of the incident. The necessary repair works were subsequently completed on Thursday, November 26, 2026, around 12:07 p.m., fully restoring the line to operation.
GRIDCo has since appealed to the general public to help protect critical electricity transmission infrastructure by refraining from illegal chainsaw operations and other activities in the vicinity of transmission lines and associated facilities.
The company expressed appreciation to all affected consumers for their patience, cooperation, and understanding during the period of the outage.
The incident highlights the severe damage and operational impact that illegal chainsaw actions have on the company’s assets and its ability to transmit power reliably across the country.