Dublin greenway quadruples in cost over building rules

A north county Dublin greenway, being built alongside a railway track that collapsed into Malahide estuary almost two decades ago, has more than…

Updated / Friday, 27 Nov 2026 17:24

Aerial view of Broadmeadow Way

Those behind the Broadmeadow Way say unusual construction restrictions have caused challenges for the project

A north county Dublin greenway, being built alongside a railway track that collapsed into Malahide estuary almost two decades ago, has more than quadrupled in cost and is two years behind schedule.

Those behind the Broadmeadow Way say unusual construction restrictions have caused challenges for the project, but that it will bring tourism and jobs to the region.

The development, which links Malahide and Donabate, has been inching across the Broadmeadow Estuary for the past three years, since building work began in 2023.

It was due to be completed this year, but is delayed until 2028 partly because most of the construction can only happen during the summer, so as not to disturb wintering birds in the estuary.

Some of the work could also only take place over a three-hour window at night, when the trains are not running.

This is because of its proximity to the railway track, which is the busiest in the country with both northern commuter and Belfast Enterprise services using it several times daily.

Aerial view of Broadmeadow Way
A senior engineer at Fingal County Council said there were many unique constraints on this project

The foundations for this project came from a near disaster almost two decades ago when in August 2009, the railway track on the Broadmeadow viaduct collapsed into the sea.

Minutes before, an Irish Rail driver travelling towards Connolly Station felt the line starting to give way and alerted other services, ensuring no trains were on the track when it gave way.

During rapid repair works, which took just three months, Fingal County Council had the foresight to ask Irish rail to sink eleven columns into the estuary.

This later allowed them to start constructing the greenway after the pandemic, but the original estimated cost of €12 million has more than quadrupled to around €50 million due to the increased cost of construction, the five-month window for the bulk of the construction and some other environmental concerns that were not foreseen at the start of the project.

Linda Lally, senior engineer for transport and infrastructure at Fingal County Council, said there were many unique constraints on this project, which engineers have had to work around.

Ms Lally said: "It's a very unique project because two kilometres of the project is built on Irish rail infrastructure, within about 10 foot of the railway line, and on the other side, we have Malahide Estuary, a special area of conservation, a special protected area so the project posed a lot of challenges.

"In the environment we are in, we couldn't pour concrete and we couldn't use a crane because you're so close to the railway line."

Linda Lally standing at the site of the project.
Linda Lally said there was 'a very tight programme to get the bridge in place'

She said those working on the project had to have a real regard for the estuary.

She said: "So, by putting our heads together, we came up with a scheme where we'd use precast concrete bridge beams, but they had to be transported in on special piece of kit.

"To do that, the weir underneath had to be levelled, and that had an impact on the water levels in the inner estuary and on the mud flats where the wildlife would reside.

"We were constrained to doing that between May and September only.

"We had a very tight programme to get the bridge in place."

Ms Lally said the railway "is national strategic infrastructure and the protection of it was one of the main objectives that we had to adhere to" alongside the protection of the estuary and environmental considerations.

Fingal County Council's CEO said those behind the work have put the environment to the fore of the project.

AnnMarie Farrelly said it is a "very technically and environmentally complex project".

She said: "We've been working on it now for a number of years.

"We've never done anything like this before in such an environmentally sensitive area. "When you get into detailed design and actual construction planning, you then have to look at the precise detail of those environmental constraints."

Annmarie Farrelly standing at the site of the project.
AnnMarie Farrelly said the greenway will be 'wonderful for the populations of Donabate and Malahide'

She said those working on the project "wanted to make sure that we delivered our project precisely in accordance with the Planning Commission, that we protected the environment so to do things too quickly, if it's not at the right time, with all the precise planning in place would be wrong.

"We have a duty to protect the environment, and I can tell you that's what has contributed to any delay that has happened."

Ms Farrelly said the greenway will be "wonderful for the populations of Donabate and Malahide".

"The population in Donabate is increasing significantly.

"There's about 1000 homes being constructed there right now. It's going to link two of our major heritage properties, Malahide Castle and Park to Newbridge Demesne and Park.

"It's going to be a destination tourism facility. "

She said Malahide Castle has about three million visitors already, with a "significant number of visitors to Newbridge House and Demesne".

At an update on the project, Fingal said the project is now at the halfway point and is expected to be finished in early 2028.