K-IV water project completion now expected by June 2027, WAPDA tells National Assembly sub-committee
- English News
- Pakistan News
- K-IV water project completion now expected by June 2027…
The first phase is designed to supply Karachi with 260 million gallons of water daily. The project, initially due in 2023, has faced delays linked to design issues.
KARACHI, (Pakistan Point News - 25th Nov, 2026) A sub-committee of the National Assembly Standing Committee on Water Resources on Tuesday reviewed progress on the Greater Karachi Bulk Water Supply Scheme (K-IV), with WAPDA officials informing the members that the project was likely to be completed by June 2027.
The meeting, chaired by Sub-committee Chairman Muhammad Idrees, discussed the project's implementation status, reasons for delays, design issues, planning and accountability for the slow pace of work.
Members sought details about the progress made so far and questioned whether anyone had been held responsible for the delays. They stressed that the project was crucial to meeting the growing water requirements of Karachi, adding that both the federal and Sindh governments were taking it seriously and its completion should not be delayed further.
Other participants included MNAs Waseem Hussain, Javed Ali Shah Jilani, Mian Khan Bugti and Amin-ul-Haque, Additional Secretary Ministry of Water Resources Mehar Ali Shah, K-IV Adviser Engineer Amir Mughal, Project Director Gul Mir Khan and other officials.
Briefing the committee, WAPDA officials said the K-IV project was conceived by the Sindh government in 2003 to address Karachi's growing demand for potable water and reduce the city's water deficit.
The feasibility study was conducted through consultants during 2006-07, while the original PC-I for Phase-I was approved by the Executive Committee of the National Economic Council (ECNEC) on July 18, 2014. The detailed design was completed in 2015, and the execution contract was awarded to Frontier Works Organisation (FWO), with civil works commencing in July 2016 and scheduled for completion by December 2018.
The officials said work continued until 2018, but design-related issues emerged. A third-party investigation commissioned by the Sindh government subsequently identified shortcomings in the project design.
They informed the committee that the federal government took up the matter in 2020 under the Karachi Transformation Plan, involving the Ministry of Water Resources in the process. WAPDA took over the project in April 2021 and began mobilisation in September 2022.
According to the briefing, the project was initially expected to be completed by October 2023. However, its revised likely completion date is June 2027.
WAPDA officials said the revised design and planning had been shared with the Planning Commission and the federal government.
The original scheme envisaged supplying 650 million gallons per day (MGD) from Keenjhar Lake in Thatta district to Karachi in three phases. Phase-I was designed to provide 260 MGD, followed by another 260 MGD in Phase-II and 130 MGD in Phase-III.
The first phase, currently being executed by WAPDA under the Ministry of Water Resources, is designed to supply 260 MGD to Karachi through three termination points at Pipri, North East Karachi (NEK) and Manghopir.
The project includes an intake structure at Keenjhar Lake, a gravity channel, pumping facilities, a pressurized pipeline, three reservoirs and filtration plants. The Sindh government is responsible for the distribution and augmentation system, power supply arrangements, land acquisition and clearance of the right of way.
WAPDA officials said Karachi's water requirement was around 1,200 MGD, underscoring the importance of completing the project to improve bulk water supply to the metropolis.
The operation and maintenance of the scheme will be undertaken by the Karachi Water and Sewerage Corporation (KW&SC), Government of Sindh.