Margalla Avenue Extension, Sangjani Interchange 43% Complete, CDA Says
The CDA says construction includes a 2.7-kilometre road extension, service roads, loops and ramps. Four of five culverts are complete, while work continues on the remaining culvert and other project sections.
ISLAMABAD, (Pakistan Point News - 23rd Nov, 2026) Development work on the Margalla Avenue extension from N-5 to M-1 and the Sangjani Interchange project has reached 43 per cent completion, with construction activities continuing round the clock, the Capital Development Authority (CDA) said on Monday.
The project includes an approximately 2.7-kilometre extension of Margalla Avenue within Islamabad Capital Territory (ICT) limits. Work is under way on different sections of the road, along with connecting service roads, loops and ramps, according to a CDA statement.
The authority said work on the loops and ramps was nearing completion, while the structural work of the underpass, including its concrete walls and footing slabs, had been completed. Earth filling on both sides of the underpass is expected to be completed shortly.
At the Sangjani Interchange, piling work has been completed, while steel fixing is under way. The CDA also reported completion of piling and girder work, with excavation work nearing completion.
Work on the N-5 bridge has also progressed, with piling and excavation for abutments on both sides completed. Of the five culverts included in the project, four have been completed, while work on the remaining one is continuing.
CDA Chairman and Chief Commissioner Islamabad Sohail Ashraf has directed the concerned authorities to ensure completion of the project within the stipulated timeframe while maintaining construction quality.
He said the project would serve as an important gateway for people travelling to Islamabad from other cities, particularly Khyber Pakhtunkhwa, and improve access to Islamabad International Airport for commuters travelling within and outside the capital.