Balochistan High Court orders fresh survey of Quetta tube wells after rejecting reports

The court said the reports on tube wells’ number and legal status were incomplete. A deputy commissioner’s report found 227 of 295 surveyed wells lacked required authorisation; authorities must report back on December 23.

QUETTA, (Pakistan Point News - 22nd Nov, 2026) The Balochistan High Court has rejected reports submitted by government authorities regarding illegal tube wells in Quetta, describing them as incomplete and unsatisfactory, and has ordered a comprehensive fresh survey of all tube wells operating in the city and its surrounding areas.

A two-member bench comprising Chief Justice Justice Muhammad Kamran Khan Malakhail and Justice Muhammad Najmuddin Mengal issued the directives while hearing a constitutional petition concerning water supply and the regulation of tube wells in Quetta, an official handout said.

During the proceedings, the court expressed dissatisfaction with a report prepared by a committee constituted by the Public Health Engineering (PHE) Department regarding illegal tube wells. The bench ruled that the findings failed to provide a comprehensive picture and consequently rejected the report.

The court also dismissed another report concerning the overall number and legal status of tube wells in Quetta, saying that it was incomplete and insufficient for judicial scrutiny.

According to a report submitted by the Deputy Commissioner Quetta East, out of 295 tube wells surveyed, only 68 possess the required No Objection Certificates (NOCs), while 227 tube wells are operating without legal authorisation.

The High Court directed the Secretary of the PHE Department to establish an effective team tasked with identifying illegal tube wells and conducting a complete survey across Quetta and its suburbs.

The court further instructed authorities to ensure strict legal action against individuals allegedly involved in illegal occupation of government-owned tube wells. Matters relating to encroachments on public tube wells have been referred to the Deputy Commissioners of Quetta East and Quetta West, who have been ordered to conduct inquiries and submit detailed reports.

The court was informed by officials of the Balochistan Water and Sanitation Authority (BWASA) that nearly 80 per cent of BWASA’s pipeline network previously used for water supply from private tube wells has already been disconnected.

Counsel for the petitioner informed the bench that seven blocks of Hazara Town are currently receiving water from nine tube wells established around Kharkhasa Dam. However, the supply remains irregular and limited, causing concern among residents.

BWASA officials further informed the court that five tube wells located near Akhtarabad Dam remain non-operational due to incomplete electrical connections, pipeline installations and other construction-related works.

Authorities stated that arrangements are also being made to channel water from four tube wells in Sariab/Sajawalabad to water reservoirs serving Hazara Town.

The court was additionally informed that residents in the eastern and western parts of Hazara Town are currently receiving water from the nine tube wells near Kharkhasa Dam on alternate days as part of an interim supply arrangement.

Expressing concern over the deteriorating condition of water infrastructure, the High Court ordered the immediate repair and replacement of damaged and worn-out pipelines to improve water distribution in Quetta.

The bench directed BWASA’s concerned engineer to complete all essential work without delay and submit a progress report at the next hearing.

Recognising the broader challenges facing Quetta’s water sector, the court instructed the Secretary PHE to prepare and submit a comprehensive report outlining a sustainable and long-term strategy for the city’s future water supply needs.

Next Hearing

The Balochistan High Court adjourned further proceedings in the case until 23 December 2026, when authorities are expected to present progress reports on the court’s directives, including the fresh survey of tube wells, investigations into illegal occupations and improvements in water supply infrastructure.